LUBRICATION(H4DOTC DIESEL) > Oil Pan Upper and Strainer

INSTALLATION

1. Install the baffle plate.

Tightening torque:

6.4 N·m (0.7 kgf-m, 4.7 ft-lb)

2. Install the O-ring to the strainer.

NOTE:

Use new O-rings.

3. Install the strainer.

Tightening torque:

6.4 N·m (0.7 kgf-m, 4.7 ft-lb)

4. Install the O-ring.

NOTE:

Use new O-rings.

5. Apply liquid gasket to the mating surface of oil pan upper.

NOTE:

Install within 5 min. after applying liquid gasket.

Liquid gasket:

THREE BOND 1217G (Part No. K0877Y0100) or equivalent

Liquid gasket applying diameter:

(A) 8.0±1.0 mm (0.3149±0.0394 in)

(B) 5.0±1.0 mm (0.1969±0.0394 in)

(C) 1.0±0.5 mm (0.0394±0.0197 in)

6. Tighten the oil pan upper installing bolts in the numerical order as shown in the figure.

Tightening torque:

18 N·m (1.8 kgf-m, 13.3 ft-lb)

7. Install the water pipe securing bolts (A) and radiator outlet hose (B) to the thermostat cover.

Tightening torque:

6.4 N·m (0.7 kgf-m, 4.7 ft-lb)

8. Apply liquid gasket to the matching surface of oil pan lower.

NOTE:

Install within 5 min. after applying liquid gasket.

Liquid gasket:

THREE BOND 1217G (Part No. K0877Y0100) or equivalent

Liquid gasket applying diameter:

5.0±1.0 mm (0.1969±0.0394 in)

9. Tighten the oil pan lower installing bolts in the numerical order as shown in the figure.

Tightening torque:

6.4 N·m (0.7 kgf-m, 4.7 ft-lb)

10. Install the engine to the vehicle.

11. Fill engine oil.